Remaining days of effort

Subscribe to Remaining days of effort 1 post, 1 voice

 
Avatar Melinda administrator 112 post(s)

Remaining Days of Effort

Ranged estimates are given in remaining days of effort. The low and high values should represent a span of time in which you’re about 80% confident your task is going to complete.

There are a couple places these values can be entered. In the work detail pane:

And from your dashboard:

Note that the remaining days of work is very different from “number of days until this task will be worked on.”

Say you have a task you expect to happen in two weeks. The remaining amount of effort (also, in this case, the total amount of effort) is 2-4 days. Rather than scheduling the task as a 12 to 14 day task (2-4 days plus two working weeks), set a delay until on the task until it should begin and enter the appropriate values for remaining days of effort.

Remaining days of effort is also a little different than task duration, since remaining days, what we schedule for, is based on the work that is left to do. For this example, consider that we had a two week task and have 2-4 days remaining. Again, enter 2-4 for the remaining days of work, not 12-14 for the total work days. We are only concerned with what’s left to do. In some cases, that may be the entire effort to complete the task, but not always.

Login to reply