Task ID more prominent
|
|
This comes to me from my offshore folks; it’s a bit tricky to see the Task ID number. I think I can only see it in Estimate view. In any case sometimes it gets a little confusing as to which task we are referring when we make assignments and try to cross reference them with incoming billing. Am I missing a way to make it more prominent? Thanks, MW |
|
|
I assume you have already found out how to add and position the Task ID column using the Actions | Advanced menu button. Currently, customizing columns is only supported on the Estimates view. There is a trick you can use to get it from other views: 1: Select the item you are interested in 2: Go to the actions menu and select “Link to selection” 3: You get a dialog box with a perma-link to that item. This is meant for emailing, but you can grab the ID from the end (e.g. “id=20279”) Also, we are working on improved hours worked features; if you would like to send us your wishlist for this area, please do so at mailto:feedback@liquidplanner.com. |