If a workitem is entered on 2/6 with a promise date of 3/4 and a duration of .15 days, the 50% estimate date returned is 3/16 even though the assigned individual has not other workitem or project assigned to him. Why is this? |
|
|
Promise dates do not effect scheduling, they act as a marker. If the expected date runs out past the promise date, then workitem will be flagged. It’s a tool for managing your expectations. Now as to the strange dates:
Barring those two situations, I can’t really guess what the situation was, however if you would like I could look at your space and try to help you figure it out. |