How do I enter an estimate for a task that may only take me a few hours to complete?

Subscribe to How do I enter an estimate for a task that may only take me a few hours to complete? 3 post(s), 3 voice(s)

 
Avatar Bruce P. Henry administrator 55 post(s)

How do I enter an estimate for a task that may only take me a few hours to complete?

In LiquidPlanner we use days as the basic unit. If you think it will take you half a day, use 0.5 days.

When entering small task, I ask myself “how many of these could I do in a day?” If it’s something that should take a quarter of my day, I’ll give it a ranged estimate of something like .2 to .4 days. The smallest unit you can use is .01 days, which is about five minutes.

 
Avatar miroslav.kacur 1 post

I guess when you mention hours, you consider only working hours right? so how many is that? 8, 10, 12 per day? i am trying to figure out wheter 0.5d = 12h or not.
i just got using LP and my very 1st impression is that i would find it very useful planning in more detailed units than days.
thanks for the reply

 
Avatar jason 5 post(s)

Right now we treat a day as 8 hours. However, we’re aware that several of our customers would like units other than days. We’re going to be building this functionality in a future release. Hopefully you can work with days until then.

Thanks,
Jason