Our forum platform uses a separate login to identify you; it's not the same as your LiquidPlanner application login.
If you wish to post and subscribe to change notifications, you will need to create a forum account.
After you login, you can access your profile by clicking your name floating at the top of the page. Clicking your name will also allow you to subscribe to e-mail change notification messages for the section you are currently looking at.
Note, the forums are a public area. Do not post any private workspace content.
Hi Donna,
Overdrive still honors dependencies and any explicit "delay untils" that you have set. So if you have two tasks with a dependency, the first one still must finish before the second one.
Given that, I would suggest sending an email to support support@liquidplanner.com, and we can walk through the schedule with you.
Thank you! I checked the schedules in the red, which I had duplicated from one master schedule. Many of them had retained the dependencies from the master schedule for some of the tasks.
I have reset the dependencies to the correct schedules and that fixed the problem.
Great, glad we could help.
|
©2010 LiquidPlanner, Inc. |
|

I have created several schedules that will be completed entirely by offsite workers. Therefore, I have assigned those tasks to virtual members and enabled the overdrive function on their accounts. However, the schedules are still going into the "red."
How is this possible? I though that overdrive scheduling was supposed to ignore member availability.