Help Guide > Reports and Analysis > Date Drift Report

Reports are located in the View Gallery.  Select a plan item, then click the desired report to see the analysis for that plan item.  To print a report, click the print view link in the header, right under the view gallery.

The Date Drift Report (a.k.a. Slip Report)

This report is like the clear light of morning streaming in an hour too early. It shows you where your project was expected to exit at any point in it’s lifetime.    Pick a point on any line, then watch the black box in the lower right to see what the projected finish date for the project was as of that point in time.  

  • The upper blue line is the worst-case (high) estimate of the finish date. 
  • The lower blue line is the best-case (low) estimate of the finish date.
  • The black line in the middle is the expected finish of the remaining work. 
  • The red line represents the deadline date for this project

Note: this report was introduced Feb 14th 2009 and will not show any trending prior to that time.