Help Guide > Tracking Time > Marking Items as Done
Marking Items as Done
When a task has been completed, mark it done via right-click > mark done, or by checking the mark done box in the work tab of the task edit pane:

- Done items will be removed from view if you have the default active items filter applied. You can open that filter box to see the filter options for viewing done items.
- Don't forget to log your final amount of progress before marking the task done. (LiquidPlanner automatically clears any outstanding remaining effort when you mark the task done, but it doesn't apply it to your timesheet.)
- When marking a container (Project, Folder, or Package) as done, all of the items within the container will also be marked as done.
- It is highly recommended to mark things as done rather than delete them. Deleting items will destroy all tracking history including timesheet entries. If an item is accidentally deleted, go to the trash view to recover it.